CAAM outlines phased taxiway rehabilitation, aircraft parking changes and new helicopter apron facilities as infrastructure works continue towards July 2027.
Penang International Airport is undergoing a major airside infrastructure upgrade involving apron expansion, taxiway rehabilitation and changes to aircraft parking arrangements, with the programme scheduled to continue until July 2027.
According to the Civil Aviation Authority of Malaysia (CAAM), the project includes improvements to existing apron taxiways, the introduction of a new helicopter apron and the development of additional aircraft stand taxilanes.
The works form part of a four-phase programme covering the period from March 2025 to July 2027. CAAM’s Aeronautical Information Publication (AIP) Supplement 38/26 identifies the first two phases as completed, with the third phase dedicated to apron taxiway rehabilitation.
Phase 3 commenced on 19 July 2026 and is scheduled to continue until 22 June 2027. The final phase, involving apron taxiway realignment, is planned from 23 June to 1 July 2027.
Taxiway Rehabilitation and Aircraft Movements
The rehabilitation works cover sections of the existing apron taxiway infrastructure, beginning between aircraft parking bays B7 and A6L before progressing towards bays A8 and A7.
CAAM’s published arrangements provide for temporary closures of Taxiways G and F in sequence, alongside restrictions affecting designated aircraft parking bays.
The precise effective dates of these operational changes are to be communicated through Notices to Airmen (NOTAMs) or subsequent AIP amendments.
During the construction period, aircraft are prohibited from entering closed movement areas. Air traffic control will determine the available taxi routes, while pilots are advised to exercise caution near excavation sites, construction equipment and personnel.
The restrictions are intended to accommodate rehabilitation activities while maintaining controlled aircraft movements within the airport.
New Helicopter Apron and Parking Facilities
The expansion programme also provides for the introduction of Helicopter Apron H1, Helicopter Stand Taxilane M and Aircraft Stand Taxilane N.
These facilities form part of the airport’s planned airside reconfiguration, although their individual activation dates remain subject to the relevant aeronautical notices.
The final phase will involve changes to aircraft parking bay configurations and the relocation of the existing Apron Taxiway K centre line.
New ground movement markings and aircraft guidance arrangements are also included in the published programme.
Operational Considerations
For airlines, business aviation operators and ground handling organisations, the phased works require continued attention to current aeronautical information and air traffic control instructions.
The published construction arrangements do not, by themselves, establish that scheduled airline services have experienced delays or cancellations.
CAAM’s documentation identifies 1 July 2027 as the scheduled completion date for the final phase, subject to any subsequent operational or project updates.
The programme represents a significant reconfiguration of Penang International Airport’s airside infrastructure as the airport continues its long-term development.